Project: OpenSAF

Open Source High Availability Middleware Generally Based on SA Forum Specifications


Milestone Summary:

Milestone Status New In-progress Completed Total Complete
4.0.0-B5

7 days late (03/05/10)

29 10 43 82 53%
4.0.0-M5 (4.0.0-FC)

Due in 2 weeks (03/26/10)

5 7 1 13 8%
4.0.0-RC1

Due in 4 weeks (04/09/10)

13 14 3 30 10%
4.0.0-GA

Due in 8 weeks (05/05/10)

0 0 0 0 0%
Release 4.1

Due in 9 months (11/30/10)

5 6 0 11 0%
3.0.0-GA

No date set

62 14 50 126 40%
PL 2.0.2

No date set

12 6 15 33 46%
PL 3.0.1

No date set

23 2 55 80 68%
PL 3.0.2

No date set

10 1 4 15 26%

Repository Statistics

Note: See TracRoadmap for help on using the roadmap.